G Mining Ventures Provides Tocantinzinho Project Update

All amounts are in USD unless stated otherwise TSX: GMIN OTCQX: GMINF Project remains on schedule and on budget for commercial production in H2-2024 Total project progress of 87% with construction 89% complete Total spending to date of $433 million (95% of project total) Updated virtual…